Port Union Beach Curb Maintenance – Completed

Toronto and Region Conservation Authority (TRCA) conducted Major Maintenance along the Lake Ontario Shoreline in Port Union Waterfront Park in the City of Toronto. As a result of the work, TRCA was able to protect the multi-use Waterfront Trail.

Project Location

The project area was located within Port Union Waterfront Park at the base of Port Union Road, along the north shore of Lake Ontario, in Scarborough.

Port Union Beach Curb Maintenance Project Area Map
Port Union Beach Curb Maintenance Project Area Map. Source: TRCA, 2022.

Scope of Work

  • Start Date: April 2022
  • Completion Date: December 2022

The scope of work for this project was to further reinforce an existing beach curb with an added armourstone revetment to provide enhanced long-term protection to the park path and Metrolinx rail line. The scope of work included the following:

  • Constructing an armourstone wall in front of the existing beach curb
  • Repairing existing beach curb
  • Constructing nearshore reef habitat features (submerged)
  • Spot repair damaged parts of Waterfront Trail

Port Union Waterfront Park shoreline before and after beach curb repair and shoreline protection work
Port Union Waterfront Park shoreline before and after beach curb repair and shoreline protection work. Source: TRCA, 2022, 2023.

Sections of the Waterfront Trail in Port Union Waterfront Park were damaged by erosion and were repaired and repaved as a part of Project work
Sections of the Waterfront Trail in Port Union Waterfront Park were damaged by erosion (left) and were repaired and repaved (right) as a part of Project work. Source: TRCA, 2021, 2023.
Material used to repair and protect the Port Union Waterfront Park shoreline was brought in by barge
Material used to repair and protect the Port Union Waterfront Park shoreline was brought in by barge. Source: TRCA, 2022.
Aerial view of the completed shoreline protection work
Aerial view of the completed shoreline protection work. Source; TRCA, 2023.
View of the Project site - now revegetated
View of the Project site, now revegetated. July, 2023

Photos

view of the project site in May 2022
May 2022
view of the project site in June 2022
June 2022
view of the project site in July 2022
July 2022
view of the project site in August 2022
August 2022
view of the project site in September 2022
September 2022
view of the project site in October 2022
October 2022
view of the project site in November 2022
November 2022
view of the project site in December 2022
December 2022
view of the project site in July 2023
July 2023

Contact Us

For more information regarding this project, please contact:

Natasha Gibson, PMP
Senior Project Manager, Erosion Risk Management
Restoration & Infrastructure Division
natasha.gibson@trca.ca
(365) 566-2342