Ashbridges Bay Park East Shoreline Maintenance Project

Toronto and Region Conservation Authority (TRCA) is undertaking maintenance work on existing erosion control structures along the eastern shoreline of Ashbridges Bay Park to protect the park from erosion and address public safety concerns.

NOVEMBER 2026
PHASE 2 CONSTRUCTION

TRCA is preparing to begin Phase 2 of the shoreline work. To support this work, the fenced construction area will be expanded. At this time, existing Phase 1 closures will remain in effect as work continues and restoration activities are completed.

Please refer to the Construction Information section to learn more about the work areas and associated park closures.

Regular updates will be provided in the Construction Progress Updates section.

Project Location

The Project Area is located within Ashbridges Bay Park, in the City of Toronto. The closest major intersection is Emdaabiimok Avenue and Lake Shore Boulevard East. The area of concern includes three existing shoreline erosion control structures (two headlands and a rubble revetment), located at the eastern limit of the park, south of Woodbine Beach.

Map of the project area within Ashbridges Bay Park. Source: TRCA, 2022.

Learn More About the Project

Project Background

Aerial view of the project area in Ashbridges Bay Park
Aerial view of the project area in Ashbridges Bay Park. Source: TRCA, May 10, 2023.

Ashbridges Bay Park is a unique artificial landform that was created as part of a lakefill project to expand lands east of Coatsworth Cut, following the development of the Ashbridges Bay Wastewater Treatment Plant.

After development, the park was opened to the public in 1977. Today, the park is used for its many amenities including an intricate trail system, marina, fishing boardwalks and picnic areas.

Erosion control structures along the shoreline of Ashbridges Bay Park have been subjected to constant wave action, ice effects and flooding since its construction.

The structures within the Project Area include two headlands and a rubble revetment. These structures and the other nearby erosion control structures have been monitored annually since 2006 as part of TRCA’s Erosion Risk Management Program (ERMP).

In the spring of 2017, Lake Ontario experienced record high water levels, which exacerbated erosion issues along the entire Toronto shoreline. On April 14-15, 2018, a severe ice storm caused high wave conditions resulting in heavy damage to many shoreline erosion control structures.

The structures within the Project Area experienced damage during both severe weather events and were inspected under the ERMP in 2019.

The rubble revetment was identified to be in a failing condition with displacement of rip rap material and scouring evident throughout the structure. This structure was listed as the highest priority for major maintenance works due to proximity of backshore erosion to the park trail.

Both headlands were identified as at-risk with displacement of armourstone material evident along both structures.

Due to the continuing instability of the area and deficiencies observed along the erosion control structures, shoreline maintenance works must be undertaken in the Project Area in order to mitigate the risk to public safety.

Backshore erosion along the beach
Backshore scouring along the erosion control revetment between the headlands. Source: TRCA, 2022.
Backshore erosion and displacement of material on the north headland
Backshore erosion and displacement of material on the north headland. Source: TRCA, 2022.

Scope of Work

The general scope of work includes the following:

  • Undertake site setup and establish staging/stockpile areas, including tree removals, installation of Erosion and Sediment Control (ESC) measures and construction fencing and tree protection
  • Prepare shoreline for maintenance including removal of existing stone and excavation where required
  • Rebuild the armourstone headlands with existing and new stone material to reinforce it
  • Resurface the rubble revetment with new cobble material
  • Install habitat stones underwater to enhance aquatic habitat
  • Complete site restoration, including reseeding and tree plantings 

Construction Information

The work area and a section of park trail will be closed to accommodate construction access. Trail crossing points will be provided at key locations along the construction access route. Work will be advanced in phases to keep as much of the park open as possible until construction reaches each section.

Phase 1 construction began in February 2026. Starting late November 2026, both Phase 1 and Phase 2 work areas are now closed.

Map of Construction Area, including phases of work, access routes, and trail crossings. TRCA, 2026.

Construction Progress Updates

November 2026

Work on Phase 1 construction is progressing well. Most of the stone placement along the slope has been completed, and work is underway to install stones along the top of the shoreline.

Construction on the shoreline for the Ashbridges Bay Park East project. Two excavators can be seen working along the shore.

October 2026

Phase 1 construction is continuing along the shoreline, with armourstone placement progressing along the south headland. Work has also begun on the aquatic habitat shoals planned along the north side of the south headland. The shoals are being constructed using 400–800 mm rip rap stone and are designed to enhance aquatic habitat along the shoreline.

August 2026

Construction activities along the shoreline are continuing as part of Phase 1.

June 2026

Work along the shoreline has progressed well.

May 2026

Site set-up activities are complete and work along the shoreline is beginning.

April 2026

Site set-up activities continue. The fencing as well as erosion and sediment control measures has been installed. The access road is being constructed.

February 2026

Construction crews have mobilized and they are starting site set-up activities.

Public Notices and Events

Notice of Construction

Notice signs are posted across the park to inform users of work area and trail closures. Click on the image below to view the Notice of Construction sign. 

Public Information Session:
November 5, 2025

A public information session was held on November 5, 2025 to inform community members of the upcoming maintenance work and share additional information about the project. You can view the information panels from this session here.

Frequently Asked Questions

Why is this work being done?

Over time, high lake levels and storm events have damaged the shoreline. Construction is needed to repair the shoreline, reduce erosion and flooding risks, and protect park infrastructure for the long term.

How long will construction take?

Construction is expected to begin in early 2026 and will take approximately two years to complete.

Will the park be open during construction?

Yes, the park will remain open during construction. Only the work zone will be closed to the public for safety reasons. This includes a segment of trail that will be used for site access.

Dedicated crossing points will be provided along the trail to maintain east–west access. Flag people may ask trail users to wait briefly while construction vehicles pass these crossing points.

Ashbridges Bay Park Road and Parking Lot 194 will also remain open, but construction vehicles will use them to access the site.

What work exactly is being done?

The work will repair two armourstone headlands and the concrete/rubble shoreline located between them. Activities include:

  • Site set-up, including installing access routes, fencing, and some tree removals
  • Repositioning existing armourstone and adding a new layer of stone along the headlands
  • Resurfacing the concrete/rubble shoreline with new cobblestone material and removing large pieces of concrete and rebar
  • Installing aquatic habitat enhancement features in the water
  • Repairing trails and planting new grass and trees
What is the extent of changes to the park?

The work being done at the park is routine maintenance and is limited to the repair of damaged shoreline erosion control structures. This is to ensure that the park has long-term protection against erosion to maintain a safe and enjoyable public space. The shoreline will be reinforced using armourstone and cobble material.

How was the repair approach decided?

Coastal engineers assessed wave action, water levels, and how the park is used to choose the most effective shoreline design and materials.

How is this work being funded?

This project is funded by the City of Toronto and also received federal grant funding from Infrastructure Canada’s Disaster Mitigation Adaptation Fund.

What is TRCA doing to protect wildlife?

Wildlife protection is a priority and TRCA is taking the following measures to limit construction impacts by:

  • Regularly inspecting the construction access route to prevent vehicles from hitting wildlife
  • Monitoring the site for nesting and other wildlife activities
  • Avoiding tree and vegetation removals during nesting periods
  • Minimizing tree and vegetation removals to only what is necessary to facilitate the construction
  • Restoring the site with only native vegetation
  • Including aquatic habitat enhancement features underwater to improve fish habitat after construction

Contact Us

For more information regarding this project, please contact the Project Team:
abp-shoreline@trca.ca