Scarborough Waterfront Project: July 28 TRCA Authority Meeting Update

On Friday, July 28, 2017, the Scarborough Waterfront Project went to the Authority. It received endorsement of the Refined Preferred Alternative and was approved to proceed to City of Toronto Council for approval to submit the final Environmental Assessment Report to the Ministry of the Environment and Climate Change.

The draft EA will be available for public review as of August 17 through October 2, 2017. All comments are to be submitted to Nancy Gaffney on or before October 2 so that they can be considered and included in the Final EA.

Prior to submission of the Final EA, TRCA will go to the City of Toronto Executive Committee and then City of Toronto Council to seek approval to submit the Final EA to MOECC for formal government review.

Additional information about these meetings will be released once the dates are finalized.