ROTARY PEACE PARK SHORELINE MAINTENANCE PROJECT

Toronto and Region Conservation Authority (TRCA), in partnership with the City of Toronto, is undertaking maintenance works on existing shoreline erosion control structures along Lake Ontario within Rotary Peace Park in order to protect against the hazards of shoreline erosion and address public safety concerns.

Project Location

The project area is located in Rotary Peace Park at 25 Eleventh Street, south of Lake Shore Drive, in Etobicoke, City of Toronto. The area of concern is located at the southern end of Rotary Peace Park, on the north shore of Lake Ontario.

Location of Rotary Peace Park Shoreline Maintenance Project. Source: TRCA, 2018.;

Learn More About the Project

Project Background

Aerial view of Rotary Peace Park. Source: TRCA, 2017.

The shoreline landform of Rotary Peace Park was built as a fill extension in the mid-1960s and includes an armourstone headland for erosion control protection. The landform has been used as a public park since its construction, and features a formal walking trail, benches, and open green space that overlooks Lake Ontario.

In 2006, TRCA began conducting annual inspections of the headland structure as a part of the Erosion Risk Management Program (ERMP). The 2006 inspection identified exposed geotextile with major displacement and voids of armourstone within the shoreline revetment. The ERMP has assessed the structure as failing since this initial inspection and has ranked it as a high priority for maintenance since 2010. Subsequent inspections have identified ongoing deterioration of the structure, including significant scouring behind the upper tiers of the armourstone wall and slumping of the revetment into the lake.

In the Spring of 2017, Lake Ontario experienced record high water levels which further exacerbated deterioration of the headland, increasing upland erosion and placing the formal park trail at-risk.

Record high water level of Lake Ontario in June 2017, causing further erosion of the Rotary Peace Park headland. Source: TRCA, 2017.
Condition of shoreline showing backshore scouring and irregular armourstone profile. Source: TRCA, 2018.
Scouring behind length of structure, putting park trail at-risk from erosion. Source: TRCA, 2018.

In 2013, TRCA retained Shoreplan Engineering Limited to develop a detailed design for repair of Rotary Peace Park’s shoreline armouring in order to address ongoing erosion concerns. The design includes reconstruction of the shoreline armouring using both original and additional new rock material, as well as the installation of a vegetated drainage swale to improve tableland drainage.

Scope of Work

The scope of work for 2018 includes project construction, which will involve the following components:

  • Site preparation, including installation of sediment and erosion control measures, as well as installation of construction fencing which will limit access to a portion of the park
  • Removal of existing armourstone structure
  • Installation of new armourstone revetment
  • Installation of vegetated drainage swale behind revetment
  • Site restoration including tree and shrub plantings

Construction Information

Construction is scheduled to commence June 18, 2018 pending the receipt of all required permits and approvals, and is anticipated to be completed by the end of April 2019.

Please note, to ensure public safety, a portion of the park, including trails within the limits of construction, will be closed to the public for the duration of the work. Amenities including the swimming pool, playground, and lawn bowling field are located outside of the work limits and will remain open. Please see the map below for details.

Location of construction activities at Rotary Peace Park. Source: TRCA, 2018.

Public Notices

The following Notice of Construction sign has been posted at all park and trail entrance locations. In addition, notice letters were delivered to surrounding residences and businesses within the project vicinity.

Progress Updates

Update: July 12, 2018

Site setup and fence installation has begun. Once setup is complete, construction of the revetment will begin.

Installation of fencing at Rotary Peace Park. Source: TRCA, 2018.

Fencing and construction equipment at Rotary Peace Park. Source: TRCA, 2018.

Update: August 1, 2018

Crews have begun dismantling the existing revetment and stockpiling armourstone and other material that can be reused.

Excavation and stockpiling of existing armourstone. Source: TRCA, 2018.

Update: September 14, 2018

Crews have dismantled the existing revetment and salvaged reusable materials. In-water works are in progress, with many stones having been placed below the water line.

Armour stones being placed below the water line. Source: TRCA, 2018.
Continuing works at Rotary Peace Park. Source: TRCA, 2018

Update: October 12, 2018

Crews have begun to place material above the waterline that will provide a base for the final armourstone revetment. Some material has been salvaged from the existing structure and reused, while other new material has been brought in.

Salvage and reuse of concrete material that was part of the original erosion control structure. Source: TRCA, 2018.
Rip Rap material placed on the shoreline. Source: TRCA, 2018.

Update: November 29, 2018

Armourstone is being placed along the shoreline on top of the established base stone.

Stacking of armourstone over the base stone. Source: TRCA, 2018.

Update: December 14, 2018

Continued placement of base stone and armourstone top layer.

Construction progress, placing base stone and armourstone. Source: TRCA, 2018.

Update: January 14, 2019

Armourstone placement continues and an access road has been established to complete works on the east side and around the nearby private property.

Progress of armourstone installation at Rotary Peace Park. Source: TRCA, 2019.
Temporary Access Road. Source: TRCA, 2019

Update: February 19, 2019

Two City of Toronto stormwater drainage pipes are present in the park. The east pipe has been excavated and will be fitted with an extension and integrated into the shoreline protection.

Excavated and exposed stormwater drain pipe. Source: TRCA, 2019

Update: March 5, 2019

The exposed stormwater drainpipe has been fitted with a new pipe extension. The pipe is being integrated into the armourstone shoreline protection. The second pipe has been excavated and the broken portions have been removed.

Integration of stormwater pipe into shoreline protection. The second pipe is visible near the black filter cloth. Source: TRCA, 2019.
Armourstone placement along eastern portion of the park. Source: TRCA, 2019.

Update: April 5, 2019

The larger stormwater drainage has been refitted with a new pipe and a concrete casing has been installed to protect it.

New drainage pipe outlet with concrete casing. Source: TRCA, 2019.

Update: April 11, 2019

All work below the water line has been completed. Crews will continue to place materials above the water line.

In water works have been completed. Source: TRCA, 2019.

Update: May 6, 2019

Armourstone has been placed up to the crest of the revetment. A drainage swale is being installed near the east parking lot.

Placement of armourstone up to the crest of the revetment. Source: TRCA, 2019.
Installation of drainage swale along east parking lot. Source: TRCA, 2019.

Update: June 6, 2019

Work on the structure has been completed and demobilization and site restoration activities are underway. Topsoil and a seed mix has been applied to the disturbed areas. Planting of trees and shrubs will begin within the next two weeks.

Completed erosion control structure with disturbed area behind under restoration. Source: TRCA, 2019.
Site restoration at Rotary Peace Park. Source: TRCA, 2019

Update: June 25, 2019

Trees have been planted along the north section of the park and shrubs have been planted along the swales. The trail and parking lots have been paved with asphalt. The paving and painting of the parking lots will be completed soon.

Repaired revetment with rip rap splash apron and planted swale. Source: TRCA, 2019.
Plantings, new asphalt trail, and growth of new grasses. Source: TRCA, 2019.

Update: July 11, 2019

Paving has been completed and the parking lots have been painted. Most equipment and project signage has been removed and the park has been reopened for public use. One project sign remains on site and small construction crews may be on-site in following weeks to do some final site clean-up.

Park conditions following construction, with vegetation being re-established. Source: TRCA, 2019.
Completion of paving and painting of the parking lot. Source: TRCA, 2019.

Update: July 17, 2019

The Rotary Peace Park Major Maintenance Project is complete and the park is open. All equipment and signage has been removed. The final site cleanup has been completed.

Aerial view of Rotary Peace Park and the recently completed headland. Source: TRCA, 2019.

Contact Us

The Planning Team is located at TRCA’s Boyd Field Centre in Vaughan:

Restoration and Infrastructure Division, Engineering Projects
9755 Canada Company Avenue
Vaughan, Ontario
L4H 0A3

For more information regarding this project, please contact Jet Taylor, Senior Project Manager.

Jet Taylor, Senior Project Manager 
Engineering Projects
Restoration & Infrastructure Division
jet.taylor@trca.ca
416-688-7627